Bioretention


Construction Schedule

Construction techniques are extremely critical in ensuring the success of a bioretention cell. Various construction guidelines and inspection points are given below, as well as a general construction schedule adapted from the Prince George's County Bioretention Manual.1

Sequence of Construction

  1. Install sediment control devices. 1/2 day

  2. Grade site to elevations shown on plan. If applicable, construct curb openings and/or remove and replace existing concrete. Curb openings should be blocked or other measures taken to prohibit drainage from entering construction area. 1 day

  3. Stabilize grading within Limit of Disturbance except for the bioretention area. 1/2 day

  4. Excavate bioretention area to proposed invert depth and scarify the existing soil surfaces, taking care not to compact the in-situ materials. 1/2 day

  5. Install underdrain system and observation wells, if specified. 1/2 day

  6. Backfill bioretention area with planting soil. 1/4 day

  7. Wet down the planting soil prior to planting vegetation to allow for settlement. 1/4 day

  8. Excavate or fill to achieve proper design grade, leaving space for the upper layer of mulch that will bring the surface to final grade. 1/4 day

  9. Plant vegetation. 1/4 day

  10. Mulch and install erosion protection at entrance points. Remove sediment control practices or entrance blocks with inspector authorization. 1/4 day

Total Estimated Construction Time: 5.5 Days

Return to top

Examples of bioretention during construction

Guidelines and Inspection Points

  • Active soil erosion control is the first line of defense against contamination of the bioretention area.

  • All sediment control devices must be in place prior to the start of the main construction.

  • Grading of any catchment area draining to the facility should be done sparingly and stabilized immediately (within 14 days).

  • A bioretention cell should not be placed in service until all of the contributing drainage area has been stabilized and approved by the inspector.

  • Soil materials should not be delivered until the bioretention site has been excavated or graded and the underdrain systems are in place. Planting materials should not be delivered until after the soil medium has had time to settle to the proper grade elevation.

  • Prior to covering the underdrain system, the inspector must observe the underdrain itself, the connections, gravel bedding, and any filter fabric. Manufacturer's tickets are required for the gravel, pipe and filter fabric material.

  • If placing gravel over the underdrain, avoid dropping it from high levels with a backhoe or front-end loader bucket. Spill directly over the underdrain and spread manually.

  • Avoid over-compaction of the soil material by allowing time for natural compaction and settlement.  No additional manual compaction of soil is necessary. To speed up the natural compaction process, presoaking the placed soil may be performed.

  • Overfill above the proposed surface invert to accommodate natural settlement to the proper grade. Depending upon the soil material, up to 20% natural compaction may occur. If construction scheduling permits, it is preferable to allow natural settlement to occur with the help of rain events.

  • The mulch layer surface should approximate the final elevation as shown on the design plans.

  • All plant materials should be tagged for identification in accordance with the American Standard for Nursery Stock.

  • The landscaping work and materials shall be guaranteed for a minimum of 1 growing season and a maximum of 2 years from the date of installation. The warrantee period begins when the as-built construction plan is approved.

References


1 The Bioretention Manual, Prince George's County Department of Environmental Resources Programs and Planning Division, Maryland, 2001.

Return to top